Tarwin Street Wetlands Stage 2 and 3
Ace Earthmoving was contracted by Baw Baw Shire Council to construct Stage 2 and 3 of Tarwin Street Wetland to treat stormwater from a Waterford Rise.
The project consisted of:
Stripping off 150mm Toposil from 30,423m2Excavation of 38,043 cubic metres of material and disposal off siteConstruction of 2 Porous Rock WiersSupply and installation of 82m of 225 diameter reinforced concrete pipe Excavation and supply of geofabric and 300-600mm rock beaching to new 1200m2 creek alignmentAll landscaping of Stage 2 and 3 of the wetlandsTopsoiling of 30,423m2 with 150mm of topsoil and establish grass cover
The project consisted of:
Stripping off 150mm Toposil from 30,423m2Excavation of 38,043 cubic metres of material and disposal off siteConstruction of 2 Porous Rock WiersSupply and installation of 82m of 225 diameter reinforced concrete pipe Excavation and supply of geofabric and 300-600mm rock beaching to new 1200m2 creek alignmentAll landscaping of Stage 2 and 3 of the wetlandsTopsoiling of 30,423m2 with 150mm of topsoil and establish grass cover